Our roadmap has no dates after six weeks. Sales survived. Here is how

September 7, 2026 · 2 min read

Six months ago our roadmap was a Gantt chart with quarter-end dates on everything for the next 12 months. Every date after week six was fiction, everyone knew it, and we kept updating the fiction anyway. Some notes on what we replaced it with, at a 40-person health tech startup.

The format

  • Now (next 6 weeks): committed, with dates. The team has estimated it and it is in a sprint plan.
  • Next (roughly 6 weeks to 3 months): the problems we intend to solve, in order. No dates. A confidence level instead: high, medium, low.
  • Later: problems we believe matter but have not validated. Explicitly allowed to disappear.

Every item is written as a problem, not a feature. "Clinics lose referrals when the receiving clinic does not respond within 48 hours" instead of "Referral reminders v2".

The sales conversation

The fear was sales. Our customers are clinics and regions, and procurement wants dates. What we actually did:

  • Sales gets the Now column with dates, and can promise those.
  • For Next, sales can say "this is the problem we are working on next, high confidence it lands this half". Our head of sales said it was easier than defending dates that moved every month.
  • For a customer who needs a date to sign, the decision goes to the leadership team, explicitly, as a trade-off: if we date this, what moves? That made the cost of a promise visible. We have done it twice in six months instead of every week.

What did not work

  • Confidence levels drifted towards "high" because nobody wanted to say "low" in front of the CEO. We now write one sentence of reasoning next to each confidence level.
  • Our board still wants a 12-month view. They get a themes slide, not a feature list. It is lagom satisfying for everyone, which is to say nobody loves it.

Not a revolution, and plenty of people have written about Now/Next/Later before. But it changed how often we lie to ourselves, which is a decent outcome for a slide. Happy to be proven wrong!

Written by

Elin Sjöberg

PM at a Stockholm health tech startup. Ex-UX researcher. Roadmaps are hypotheses, not promises. Fika is a ritual, not a break. she/her

Get the best of #roadmap_roulette weekly

One email each Monday with the most useful posts. No spam; unsubscribe in one click.

Comments

8

Sign in to join the conversation.

Sign in to comment
Rachel Kim@rachelkim#2 in Roadmap Roulette
This is the cleanest description of Now/Next/Later I've read, and the 'one sentence of reasoning next to each confidence level' fix is new to me. Confidence inflation in front of the CEO is so real. Stealing.
1 net votes
Karl Lindqvist@kernel_karl#4 in Roadmap Roulette
"Explicitly allowed to disappear" is the most honest thing a roadmap has ever said.
1 net votes
Elin Sjöberg@elin_pm#1 in Roadmap Roulette
Thank you Karl. I will try not to say 'lagom satisfying' in front of you again.
0 net votes
Karl Lindqvist@kernel_karl#4 in Roadmap Roulette
Too late. It is in my quotes file, next to 'alignment'.
2 net votes
Dhruv Thakkar@dhruv_ships#7 in Roadmap Roulette
for Indian SMB sales this would never work bhai, every customer wants a date AND a discount 😂 but the 'if we date this, what moves' framing I will steal for my own head
3 net votes
Chloe Barnes@chloebuilds#7 in Roadmap Roulette
we're 4 people and i still put dates on everything because my brain likes boxes. this might cure me. or i'll make a now/next/later board with dates on it. we'll see
2 net votes
Alasdair Reid@onprem_or_die#7 in Roadmap Roulette
no dates. aye that'll go down well wi the NHS procurement folk
1 net votes
Elin Sjöberg@elin_pm#1 in Roadmap Roulette
The Now column has dates. Procurement buys what exists, not what is promised. Happy to be proven wrong on the NHS specifically.
1 net votes